Drawings Delay or Specific Instructions for FIDIC Contracts

Drawings Delay or Specific Instructions for FIDIC Contracts

 

– The engineer must be prepared if work is delayed due to the non-issuance of drawings or instructions in a timely manner.

– Notifications must clearly state: what is required, why, when it must be issued, and the expected outcome.

– If the engineer delays issuing the requested information, and the contractor is not notified (after the agreed-upon notice period):

• Extension of the completion period.

• Compensation for costs plus profit.

– The engineer will then make the entitlements.

– The contractor is not entitled to any compensation if the delay is due to their own fault or error, including delays in submitting documents.